AIW crews were tasked with unloading two used 40' silos, standing them up and into position, then anchoring, and installing the catwalk between the two units.
http://video214.com/play/G30CLwrooFnQEVARWhW0Tg/s/dark
Two cranes were used to stand up the silos. Gusting winds made this job a challenge, however the silos were still set and anchored in one day.
Because these were used silos the catwalk was cut into multiple pieces for transportation. Steel fabrication was necessary to put the catwalk back together and complete the installation.